295(Solved): Server Rack(12U) installation at IRP1 DTW area (Total 22 DTWs)
2023-05-17:
01. DTW101 : 12U rack install done, Fiber maintenance done, power cable wiring done.
UTP cable maintenance pending ( Unavailable at SKWP store)(03/05/2023), 3nos
camera connect to PoE switch.(06/05/2023)
02. DTW102: 12U rack install done, power cable wiring done.(06/05/2023)
03. DTW103 : OPTICAL WORK DONE. CAMERA CABLE WIRING DONE, RACK INSTALLING
DONE,POWER CABLE WIRING DONE. ( 3PIN SOCKET INSTALL PENFING, SUPPORT ANGLE
WORK PENDING) 07/05/2023
04. DTW104 : 12U rack assamble & install done, power cable wiring done.
05. DTW105 : 12U rack assamble & install done, power cable wiring done.
06. DTW106 : Installed before .
07. DTW107 : 12U rack assamble & install done, power cable wiring done.
08. DTW108 : Not Available
09. DTW109 : C.C Tv rag assamble & install done, Power cable wiring done.
10. DTW110 : C.C Tv rag assamble & install done, Power cable wiring done.
11. DTW111 :
2023-05-23: Status changed to Ongoing -by: MD ABDUL MOMIN
2023-05-23 12:43:15pm: Only two ups taken from DTW101(deliverd to storekeeper), DTW103(in ICE lab), other ups are still connected with the CCTV network. This was not in plan. Please remove the old ups from the system asap and connect the CCTV system with the main ups. Work sincerely please. Give update time to time. -by: Zahid Hossain
2023-05-25 03:29:22pm: Status changed to Pending, Because of: DTW111 12U server rack 70% work done. Today Mr. Jamal (supervisor) says due to leck of manpower. He cannot manage manpower for this work. -by: Parves
2023-05-25 03:34:40pm: What about of those ups taken from DTW101 and DTW103, is it functionable? -by: Zahid Hossain
2023-05-25 03:49:59pm: Status changed to Ongoing, Because of: UPS of DTW101 indicates fault signal always, No back up.
UPS of DTW103 indicate fault signal, Can't be stable in normal mood, No back up. -by: Parves
2023-05-25 04:08:52pm: Make a separate work order for repairing all faulty ups taken from the DTW. -by: Zahid Hossain
2023-05-25 04:30:57pm: Scheduled at 2023-05-27, Required entity: Man power
1.kazi jewal
2.Rasel mizi
3.Safayet
4.Ashraf
Note: need Vehicle support
This job is very urgent
-by: Md. Ruhul Amin
2023-05-27 05:23:10pm:
DTW111: Server rack installation complete. Full day engage with this work(Rasel Miji, Reajul Islam, Safaet, Kazi Jewel). -by: Zahid Hossain
2023-05-28 04:40:31pm: Status changed to Ongoing, Because of: DTW-113 12U CCTV server rack assamble work done. Mounting work pending due to IRP1 & IRP2 FIT calibration schedule. -by: Parves
2023-05-29 04:38:08pm: Status changed to Ongoing, Because of: Dtw-113 12U CCTV server rack installation complete. -by: Parves
2023-05-29 05:15:17pm:
-by: Zahid HossainManpower:
1. Rasel Miji 2.
2023-05-30 04:57:53pm: Status changed to Solved, Because of: 12.DTW112 C.C camera rack install & power connection work complete Today -by: Md. Reajul Islam Reaz
2023-05-30 05:00:29pm: Status changed to Ongoing, Because of: Dtw-114 12U server rack installation work done. -by: Md. Reajul Islam Reaz
2023-05-31 07:05:48pm: Status changed to Ongoing, Because of: DTW115-C.C camera rack Install Work complete Today -by: Md. Reajul Islam Reaz
2023-06-12 07:53:36am: Status changed to Ongoing, Because of: DTW116 Server rack install work complete -by: Md. Reajul Islam Reaz
2023-06-12 06:25:26pm: Status changed to Ongoing, Because of: DTW119 server rack pannel installation work complete today -by: Md. Reajul Islam Reaz
2023-07-18 01:01:08pm: Status changed to Solved, Because of: OK -by: Zahid Hossain