334(Solved): Calibration Of FIT- 2001, 3001 (IRP#02)

Posted on 23rd May 2023, 1:29pm by [email protected]

2023-05-23 02:40:44pm: Status changed to Hold, Because of: Next 28.05.2023 with HEC and another person we will start the work.(Nadim) -by: Zahid Hossain
2023-05-25 10:55:40am: Scheduled at 2023-05-28, Required entity: Team ICE, HEC, Nadim (SO). -by: Zahid Hossain
2023-05-28 01:35:46pm: Status changed to Ongoing, Because of: Okay everything, manpower is enough -by: Zahid Hossain
2023-05-28 02:59:17pm: Status changed to Ongoing, Because of: 2 hours Data of FIT-3004 (IRP-2) 11:00- 51864 m3 11:20- 52748 m3 11:40- 53638 m3 12:00- 54531 m3 12:20- 55432 m3 12:40- 56324 m3 01:00- 57210 m3 -by: Parves
2023-05-29 05:11:15pm: Status changed to Solved, Because of: Work finished. -by: Zahid Hossain

No Attachment Found

No Feedback from Field Yet